Tirana – Durres railway

Integrated Tenders

Client: Ministry of Transport of Albania - Albanian Railways

Learning outcomes

The rehabilitation of the existing Durres-Tirana (PTT) railway line according to European standards, the improvement of railway infrastructure and services, ensuring high safety and interoperability.
The construction of the new railway connection/branch with Tirana International Airport.
The installation of a modern signaling and telecommunications system.
Resolving accessibility and line crossing problems (securing the system).
The improvement of existing technological systems, resulting in an increase in the speed and load capacity of each axle, in line with European standards, which will contribute to the future extension of the Albanian railway network towards the south and towards the Eastern Balkans.
The project of the Durres – Tirana Public Transport Terminal (PTT) railway line and the new railway connection with the Airport (TIA) consists of:

  • Section “A” 34.170 meters long which connects Durazzo to Tirana (PTT Terminal)
  • a new triangular intersection towards Tirana International Airport (TIA)
  • “Route C”, 5.697 meters long, new railway connection between Rinas Airport (TIA) and the new Tirana – Durazzo line.
  • YEAR OF COMPLETION

    being defined.
  • AMOUNT

    €70m
  • PERFORMER

    INC SpA
  • OBJECT

    Final and executive design, construction and commissioning

Main data

Track

41.5

km in length

Ski resorts

7

Artificial tunnel

1

229 m in length

Bridges

9

2 new and 7 demolished and rebuilt